Back

IRS/2022/582/PON10

Notification details

Status Completed
First observed date 04 January 2022
First observed time 12:00
Organisation involved PERENCO UK LIMITED
Installation 18B
Field INDEFATIGABLE [PERENCO]
Latitude 53° 23' 33.0'' N
Longitude 2° 31' 30.0'' E
Quadrant / block no. 49 / 18

Breached conditions details

Related to a breach of a condition of an approved Consent to Locate Yes
Breach related to Consent Condition and Marking Schedule Condition
Breached conditions 1. Consent Validity, 2. Description of Works, 3. Location of Works, 4. Commencement of Works, A 3. Lights

Lights breached conditions

Primary white lights lost Yes

Formal investigation

Formal investigation ever opened No

Further details

Installation fully compliant with its Consent to Locate conditions Yes
Non-compliance reasons related to Fog Signals, Loss of Primary Power, Main Lights, Operations during the Works
Loss of power Yes, primary only
Loss of power date 04 January 2022
Loss of power time 12:00