IRS/2023/2463/PON10
Notification details
Status | Completed |
---|---|
First observed date | 18 February 2023 |
First observed time | 17:15 |
Organisation involved | TAQA BRATANI LIMITED |
Installation | Harding Platform |
Field | HARDING |
Latitude | 59° 16' 46.0'' N |
Longitude | 1° 30' 58.0'' E |
Quadrant / block no. | 9 / 23 |
Breached conditions details
Related to a breach of a condition of an approved Consent to Locate | Yes |
---|---|
Breach related to | Consent Condition and Marking Schedule Condition |
Breached conditions | 5. During the Works, A 3. Lights |
Lights breached conditions
Subsidiary red lights lost | Yes |
---|
Formal investigation
Formal investigation ever opened | No |
---|
Further details
Installation fully compliant with its Consent to Locate conditions | Yes |
---|---|
Non-compliance reasons related to | Secondary Lights |
Loss of power | No |