IRS/2023/2677/PON10
Notification details
| Status | Completed |
|---|---|
| First observed date | 13 April 2023 |
| First observed time | 06:00 |
| Organisation involved | NEO ENERGY RESOURCES UK LIMITED |
| Installation | Claymore A Platform |
| Field | CLAYMORE |
| Latitude | 58° 26' 58.0'' N |
| Longitude | 0° 15' 13.0'' W |
| Quadrant / block no. | 14 / 19 |
Breached conditions details
| Related to a breach of a condition of an approved Consent to Locate | Yes |
|---|---|
| Breach related to | Consent Condition and Marking Schedule Condition |
| Breached conditions | 5. During the Works, A 3. Lights |
Lights breached conditions
| Secondary lights were not in operation | Yes |
|---|
Formal investigation
| Formal investigation ever opened | No |
|---|
Further details
| Installation fully compliant with its Consent to Locate conditions | Yes |
|---|---|
| Non-compliance reasons related to | Main Lights |
| Loss of power | No |