IRS/2023/2798/PON10
Notification details
| Status | Completed |
|---|---|
| First observed date | 10 May 2023 |
| First observed time | 17:30 |
| Organisation involved | BP EXPLORATION OPERATING COMPANY LIMITED |
| Installation | Clair Phase 1 Platform |
| Field | CLAIR |
| Latitude | 60° 41' 30.0'' N |
| Longitude | 2° 32' 40.0'' W |
| Quadrant / block no. | 206 / 08 |
Breached conditions details
| Related to a breach of a condition of an approved Consent to Locate | Yes |
|---|---|
| Breach related to | Consent Condition excluding Marking Schedule Condition |
| Breached conditions | 10. Consent non-compliance |
Formal investigation
| Formal investigation ever opened | No |
|---|
Further details
| Installation fully compliant with its Consent to Locate conditions | No |
|---|---|
| Non-compliance reasons related to | Fog Signals |
| Loss of power | No |