IRS/2023/3378/PON10
Notification details
Status | Completed |
---|---|
First observed date | 01 October 2023 |
First observed time | 14:40 |
Organisation involved | ENI ENERGY E&P UK LIMITED |
Installation | Cygnus B Platform |
Field | CYGNUS |
Latitude | 54° 35' 59.0'' N |
Longitude | 2° 11' 41.0'' E |
Quadrant / block no. | 44 / 11 |
Breached conditions details
Related to a breach of a condition of an approved Consent to Locate | Yes |
---|---|
Breach related to | Consent Condition excluding Marking Schedule Condition |
Breached conditions | 10. Consent non-compliance |
Formal investigation
Formal investigation ever opened | No |
---|
Further details
Installation fully compliant with its Consent to Locate conditions | Yes |
---|---|
Non-compliance reasons related to | Primary Power Supply |
Loss of power | No |